KTN Logistics

Projects

KTN Logistics

Project Overview

GROUP Deep Foundations was tasked with a pile installation for two large foundations at Katoen Natie Gulf Coast’s Lolita, Texas, location. Throughout the duration of the project, GROUP was able to maintain two company-owned driving rigs and all associated handling equipment, allowing the team to install well over 100 piles per day. GROUP’s experienced supervisors and crews, paired with their sequenced construction techniques, allowed for delivery beyond expectations with no quality or safety issues.

Construction Included:

  • Installation of 4,258 16” piles with a test pile program
  • Completion 10 days ahead of schedule
  • Zero recordable incidents